Pengurasan Saluran Phb Setiabudi Capai 70 Persen

Setiabudi Connecting Channel Dredging Work Reaches 70 Percent

South Jakarta Water Resources (SDA) Sub-agency dredged connecting channel in Setiabudi One area, Karet Urban Village, Setiabudi. It was done as part of channel normalization.

This dredging work is carried out as a part of water channel normalization

Setiabudi Sub-district SDA Unit Head, Yansori mentioned, his side dredged connecting channel as long as 1,180 meters from the upstream in Perbanas Campus to downstream in Setiabudi Barat Reservoir which crosses three urban villages, namely Karet Kuningan, Karet, and Setiabudi.

"This dredging work is carried out as a part of water channel normalization in order to increase its capacity. Currently we are dredging channel in Setiabudi One," he informed, Thursday (3/25).

300 Sacks of Mud from Channel on Jalan Hadiah Jelambar Transported

In dredging the channel, his side deployed one heavy equipment and seven personnel. His side dredged silt with thickness about 30-100 centimeters.

"Dredging work has been carried out since November 24, 2020 and its process has reached 70 percent. It is estimated to finish by the end of April 2021," he closed.

Linked News
Popular News indeks
  1. Pram-Rano Attend Bung Karno Festival at Proklamasi Park

    access_time20-06-2026 remove_red_eye1087 personFolmer
  2. JIS-Ancol Integrated Infrastructure Officially Activated

    access_time23-06-2026 remove_red_eye569 personDessy Suciati
  3. Free Cake-Making Training Held at RPTRA Mustika Ratu

    access_time23-06-2026 remove_red_eye486 personNurito
  4. Metropolitan City Rally 2026 to Be Held at City Hall

    access_time19-06-2026 remove_red_eye472 personAldi Geri Lumban Tobing
  5. Rano Officially Opens Discover Betawi Art and Culture 2026

    access_time19-06-2026 remove_red_eye469 personBudhi Firmansyah Surapati